  • Atlantic Lithium (A11) awards its front-end engineering design contract for the Ewoyaa lithium project to engineering company, Primero
  • Primero will help to advance the Ghana-based project to becoming a robust lithium-producing mine by providing its services for a few key tasks
  • The contract is valued at US$980,000 (A$1.45 million) and will be paid via a three-stage earn-in agreement with Piedmont Lithium to fund the project towards production
  • Atlantic Lithium expects to announce an MRE for Ewoyaa in Q1 2023 and will use that to support the planned DFS, expected to be completed by mid-next year
  • Shares in Atlantic Lithium are down 2.92 per cent, trading at 66.5 cents at 1:50 pm AEDT

Atlantic Lithium (A11) has awarded its front-end engineering design contract for the Ewoyaa lithium project in Ghana to Primero, a vertically-integrated engineering group.

Primero will provide its services for a number of tasks including optimising the project’s flow sheet, identifying long lead items and maximising the project’s long-term profitability.

Ultimately, Primero will support the advancement of the project towards becoming a financially and operationally robust lithium-producing mine.

The contract is valued at US$980,000 (A$1.45 million) and will be paid via a three-stage earn-in agreement with Piedmont Lithium to fund the project towards production.

Concurrently, Atlantic Lithium has appointed experienced mining professional Roux Terblanche as Project Manager effective immediately.

Mr Terblanche has over 25 years of experience across domestic and international mining sectors and was part of the team that delivered the pre-feasibility study for the Ewoyaa project.

Atlantic Lithium Executive Chair Neil Herbert said the contract award is the next significant step towards becoming a lithium producer.

“The award of the contract to Primero and Roux’s appointment as project manager demonstrate the significant steps we are taking to advance the project towards production,” Mr Herbert said.

“Following the recent completion of the drilling program at the project, we look forward to announcing an updated mineral resource estimate (MRE) in the coming months, which will put us in good stead to announce the definitive feasibility study (DFS) in mid-2023.”

The MRE is expected to be announced in Q1 2023, which will then be used to support the planned DFS, expected to be completed by mid-2023.

Shares in Atlantic Lithium were down 2.92 per cent, trading at 66.5 cents at 1:50 pm AEDT.

A11 by the numbers
More From The Market Online
Market Close Graphic

ASX Market Close: Index pulls back over China concerns | October 18, 2024

The bourse’s losses accumulated throughout the day, as investors remain nervous about the strength of the…
The Market Online Video

ASX Market Update: Index dragged by falling commodities | October 18, 2024

Commodity stocks have been a drag on the market, as investors await a slew of fresh…
Australia chart concept

Week 42 Wrap: HotCopper’s top picks; new ASX 200 record; world yawns at war

What HotCopper watched on the ASX this week felt a bit like 2022 – a lithium…
Zocalo Square in Mexico City

Mithril’s drilling in Mexico picks up silver at 997g/t, gold at 28g/t

Mithril Silver and Gold Ltd has seen its share price rise more than 15% on high-grade…