Mining initially began at Mt Marion in 2016 as an open-pit lithium mine.
The Market Online - At The Bell

Join our daily newsletter At The Bell to receive exclusive market insights

  • Capital expenditure estimated at $490 million.
  • Upgrade supports mine life through access to additional mineral resources.
  • Payback period at the current spot spodumene price of less than one year.
  • Removing lower-grade product to deliver a single product.

Mineral Resources (ASX:MIN) has continued to reboot its Australian lithium business with a positive final investment decision on a $490 million investment in the Mt Marion project in Western Australia.

Listen to the HotCopper podcast for in-depth discussions and insights on all the biggest headlines from throughout the week. On Spotify, Apple, and more

MinRes and joint venture partner Jiangxi Ganfeng have given the go-ahead to construct a flotation plant and develop underground mining at the Mt Marion lithium operation.

The total capital investment is comprised of a $240 million flotation plant, $220M in underground pre-production development and $30M in non-processing infrastructure.

MinRes’ MD, Chris Ellison, said the payback period at the current spot spodumene price of approximately US$2,700 per tonne is less than one year.

“This high-return brownfield investment sets up Mt Marion for decades to come,” he said,

“Underground mining and flotation will work together to access deeper high-grade ore, lift recoveries and produce a single five per cent product.”

Mining initially began at Mt Marion in CY16 as an open-pit lithium mine. From FY28, Mt Marion will operate as a combined open-pit and underground operation, with underground ore from open stoping supplementing up to 40% of processing feed.

The combination of a flotation plant with underground mining is expected to support mine life by providing access to additional mineral resources below the existing open pit and improve plant recovery towards 70%.

Tendering for an underground mining contractor is in progress, with the central underground development expected to commence in Q1 FY27.

Construction is targeted to commence in Q1 FY27, with commissioning and ramp-up expected in 2H FY28.

Earlier this month, MinRes restarted operations at its 100%-owned Bald Hill lithium mine. Mr Ellison said that decision was underpinned by a significant and sustained recovery in lithium prices, supported by diligent planning over recent months.

Bald Hill was placed on care and maintenance in late CY24 to preserve capital and retain the value of sizeable mineral resource until market conditions improved.

Restart costs, to be incurred in Q4 FY26, including working capital, are estimated at $20M.

MIN is steady at $71.91. Mkt cap $14.05B.

Join the discussion: See what HotCopper users are saying about Mineral Resources Ltd and be part of the conversations that move the markets.

The material provided in this article is for information only and should not be treated as investment advice. Viewers are encouraged to conduct their own research and consult with a certified financial advisor before making any investment decisions. For full disclaimer information, please click here.

min by the numbers
More From The Market Online
Lawsuit market concept

Optimism around Guzman Y Gomez’s US exit falters as company hit by class action

When Guzman Y Gomez (ASX:GYG) late last week announced it was exiting the U.S.

Terrain Minerals adds four new lines to Smokebush IP survey

Terrain Minerals has significantly expanded its exploration activities at the Smokebush project in Western Australia.

WIN Metals obtains early high-grade gold results from new Princess Royal asset

WIN Metals has received positive reconnaissance sampling results from its new Princess Royal gold mine in…

American T&A defines broad tungsten targets at Tennessee Mountain before 29-hole maiden drill program

American T&A has lined up key targets for its 29-hole maiden drilling program at the Tennessee…