PriceSensitive

Arafura Resources (ASX:ARU) increases Nolans Project mine life by 10 years

Mining
ASX:ARU      MCAP $850.4M
11 March 2020 17:00 (AEDT)
Arafura Resources (ASX:ARU) - General Manager, Richard Brescianini

Sourced: Arafura Resources

Arafura Resources (ARU) has provided an update of the ore reserve at its Nolans project in the Northern Territory.

The company has reported a 54 per cent increase in ore reserves to 29.5 million tonnes. This now supports a 33-year mine life, which is an increase of 10 years.

Nolans is a neodymium and praseodymium (NdPr) mine located 135 kilometres north along the Stuart Highway from Alice Springs.

Neodymium and praseodymium are rare-earth metals, well-known in the automotive and industrial power industries.

With this new ore reserve, Arafura is expecting to produce approximately 4,325 tonnes per annum of NdPr oxide at an operating cost of US$24 per kilogram. This costing estimate is based on the cost and pricing assumptions used in the DFS.

Managing Director Gavin Lockyer said the reduction in operating costs cements Arafura as one of the lowest-cost NdPr producers in the world.

“I challenge anyone to find a better fully permitted, fully costed NdPr-focused project outside China,” he said.

“It meets all the criteria to be a long term, sustainable supplier of critical minerals into clean energy technologies, and will deliver intergenerational benefits in a part of Australia that is challenged by limited opportunities for genuine economic development,” he added.

The ore reserves estimate has been independently prepared by leading mining technical services provider Mining Plus.

Arafura is up 3.17 per cent on the market today and is trading at 6.5¢ apiece at 3:02 pm AEDT.