First ore delivery in crusher and ROM stockpiles at the Edna May mine. Source Forrestania Resources ASX announcement November 23, 2026.

Forrestania Resources (ASX: FRS) is on target for an early Christmas present with further progress in the development of its key Edna May gold mine in Western Australia.

The company has achieved the successful delivery of first ore into the primary crusher at Edna May, with wet commissioning activities underway.

Executive chairman, David Geraghty, said the milestone represents a major step toward first gold production, which remains targeted for December 2026.

“Today’s delivery of first ore into the crusher is a landmark achievement for Forrestania and a significant step in our transition to gold producer with first gold pour planned in December 2026,” he said.

“Since the formal handover of Edna May on 4 September, our team has moved rapidly from site transition and refurbishment activities to crusher feed and wet commissioning in little more than two months, highlighting the quality of the asset and the capability of our people.

“Over the past year Forrestania has transformed from an exploration company with approximately 300,000 ounces of mineral resources into a business with more than three million ounces of mineral resources, two processing hubs and a substantial pipeline of ore supply opportunities. Today’s milestone demonstrates our ability to execute on that growth strategy.

“With more than 250,000 tonnes of ore stockpiled across Edna May and Lake Johnston, wet commissioning now underway and SAG mill liners now on site, we are well positioned as we advance towards first gold production.”

Ore feed through the crusher and wet commissioning activities are now underway as part of the company’s staged commissioning program. Commissioning will continue across key process plant circuits as operational performance is progressively tested and optimised ahead of first gold production.

The company is building a leading WA gold business through two strategic processing hubs at Edna May and Lake Johnston.

Forrestania’s portfolio supports a hub-and-spoke growth strategy, with multiple deposits, development assets and exploration projects located within haulage distance of existing processing infrastructure.

The company is advancing a growing inventory of ore sources at Edna May, while progressing Lake Johnston as a second strategic hub to support future growth and regional consolidation.

Through disciplined exploration, targeted acquisitions and project development, Forrestania is focused on growing its resource base, expanding production opportunities and creating long-term shareholder value.

FRS was steady at 25.5¢  with a Mkt cap of $614.2M prior to markets opening.

Join the discussion: See what HotCopper users are saying about Forrestania Resources and be part of the conversations that move the markets.

The material provided in this article is for information only and should not be treated as investment advice. Viewers are encouraged to conduct their own research and consult with a certified financial advisor before making any investment decisions. For full disclaimer information, please click here.