Pumping activities below XC11 immediately in front of decline sump, Stringbean Alley decline.
The Market Online - At The Bell

Join our daily newsletter At The Bell to receive exclusive market insights

  • Dewatering of 900m long Stringbean Alley decline nearing completion
  • New underground mine power centre undergoing final construction and commissioning
  • Complete restoration of services for underground planned for mid-August
  • Phase two underground HQ diamond drilling program planned

Haranga Resources (ASX: HAR) has commissioned a staged rapid restart program associated with a commencement of mining and milling at the Lincoln gold project in the Motherlode region of California.

Listen to the HotCopper podcast for in-depth discussions and insights on all the biggest headlines from throughout the week. On Spotify, Apple, and more.

The restart program is now well underway with mining and milling studies progressing and are intended to provide an estimate of costs and production profile associated with a commencement of mining and milling at Lincoln.

Chairman, Michael Davy, said since delivering the maiden JORC mineral resource estimate (MRA) at Lincoln, the company has undertaken substantial technical work and detailed planning to determine the most efficient, cost-effective and disciplined pathway for advancing the project.

“We are now preparing for the next intensive phase of activity, while continuing to pursue the dual-track strategy of resource growth and rapid restart outlined in our corporate presentation,” Mr Davy said.

“We continue to believe Lincoln has significant potential for multi-million-ounce resource growth, alongside the prospect of a rapid restart. We believe the best outcome for shareholders will be achieved by advancing both opportunities in an intelligent and cost-conscious manner, while leveraging the project’s existing infrastructure, historical workings and extensive historical data.

“In parallel, we continue to assess suitable candidates for the position of managing director. “Together with the recent appointment of our new independent technical non-executive director, Scott Jackson, this process reflects our commitment to assemble the strongest team possible to advance the company’s resource growth and rapid restart aspirations.”

Company personnel are currently reviewing opportunities that could support further mineral resource growth, improve resource confidence, and define additional exploration targets across the broader Lincoln gold project. This includes the possibility of the potential to convert most of the South Spring Hill exploration target to an Inferred mineral resource.

HAR was steady at 8.1¢. Mkt cap $36.66M.

Join the discussion: See what HotCopper users are saying about Haranga Resources and be part of the conversations that move the markets.

The material provided in this article is for information only and should not be treated as investment advice. Viewers are encouraged to conduct their own research and consult with a certified financial advisor before making any investment decisions. For full disclaimer information, please click here.

har by the numbers
More From The Market Online
The Market Online graphic with ASX-branded charts and the text "HotCopper Highlights" centred in white.

HotCopper Highlights, Week 32: Rare earths, lithium, and gas dominate conversations

This week's most viewed and most discussed ASX stocks include Anson Resources, Liontown, Elixir Energy, Invictus…

Connected Minerals advances maiden drill program at Ballundo

Connected Minerals has confirmed exploration and mobilisation activities are being ramped up at the Bailundo carbonatite…

Tivan agrees to project finance mandate for Speewah fluorite project

Tivan reports that ICA Natural Resources has been appointed to advise on project finance for the…

Aurum Resources hits bonanza gold section at Boundiali

Aurum Resources has hit bonanza gold intercepts from an ongoing 100,000m diamond drilling program at the…