  • Mount Gibson Iron (MGX) provides quarterly update for June quarter which focused on its Western Australia-based projects
  • The company progressed an overburden stripping program at Koolan Island to eventually access larger amounts of higher-grade iron ore
  • MGX has also begun production at the Shine Iron Ore Project which is slated to produce 1.5 million wet metric tonnes per annum over an initial two years
  • At the end of the quarter, cash and investments fell from $412 million to $365 million after development and capital costs at Koolan Island and Shine
  • Company shares are down 7.65 per cent and trading at 90.5 cents

Mount Gibson Iron (MGX) has recapped its activities during the June quarter which was largely spent advancing its Shine Project and Koolan Island operation.

Koolan Island

Mount Gibson Iron continued its overburden stripping program at the Western Australian operation. This is required to access larger volumes of higher-grade iron ore from later this year and onwards.

A total of five million wet metric tonnes moved during the quarter which marks a 13 per cent increase. The increase in total material movement reflects the ramp-up in waste movement after the end of the wet season.

Mining to the west of the Main Pit experienced significant impacts from a surface rockfall and continues to be impacted by COVID travel restrictions.

This footwall program will allow mining access to high-grade ore zones in the lower western end and central parts of the pit from September onwards.

Positively, ore sales rose from 232,000 wet metric tonnes in the March quarter to 481,000 wet metric tonnes at an average grade of 56.6 per cent iron.

But as previously indicated, production and sales will be limited to lower and medium-grade material until the upper footwall works have progressed.

Shine

The WA-based Shine Iron Ore Project has an initial ore reserve of 2.8 million tonnes at 59.4 per cent iron in the proposed stage one pit.

Prior to the quarter, MGX cleared the open pit footprint and began blasting and mining in late March. The first ore was mined and stockpiled in early April and TTM was 1.8 million wet metric tonnes including 55,000 wet metric tonnes of sales-grade ore.

Site construction work is mostly complete and the project has officially begun production with annual production forecast to be 1.5 million wet metric tonnes over an initial two years. The first ore shipment from the Geraldton Port is targeted for next month.

At the end of the period, Mount Gibson Iron had $365 million in cash and investments which marks a notable decrease from the $412 million it had at the end of the March quarter.

The $47 million reduction reflects capital and development costs for both projects.

Company shares were down 7.65 per cent and trading at 90.5 cents at 1:08 pm AEST.

MGX by the numbers
More From The Market Online

Quarterly wrap: Infini Resources, Barton Gold & Infinity Lithium

It's quarterly season, and there's a lot to take in. Here's the big takeaways for Infini,…
The Market Online Video

Market Close: ASX signs off on a sigh with all sectors red-lining

The ASX200 finished 1.3 per cent down with every sector in the red and Industrials and Real Estate brittle and bruised as bot…

Trinex Minerals had a hot winter on high grade Uranium hits in Canada

Trinex Minerals has intercepted high grade uranium at the Gibbons Creek Uranium Project in Canada after…