- SEPP successfully energised and connected to the South West Interconnected System (SWIS)
- AEMO hold-point testing now underway
- $187 million investment
- Commercial operations targeted following completion of AEMO hold-point testing
Strike Energy (ASX: STX) has successfully energised the 85 MW South Erregulla Power Plant in WA, marking completion of construction and a major milestone in the company’s strategy to create long-term value through integrated energy infrastructure.
Energisation was completed on 20 November 2026 in conjunction with Western Power and enabled commencement of hold-point testing activities with the Australian Energy Market Operator (AEMO) which are expected to commence immediately and forecast to take approximately six to eight weeks, ahead of commercial operations in late January 2027.
The 85MW gas-fired peaking facility is now physically connected to Western Australia’s SWIS and is positioned to benefit from growing demand for flexible, dispatchable generation as State-owned, coal-fired capacity is progressively retired by 2030.
AEMO hold point testing activities will see the facilities output progressively increase from 10 MW to full nameplate capacity of 85MW, in stages, known as “Hold-Points”, with testing at each level to confirm that the facility responds correctly to changes in grid voltage and frequency and matches technical models and expectations. Results are reviewed by AEMO and Western Power, and the station only progresses to the next stage once approved. During commissioning, electricity dispatched into the grid earns revenue at prevailing spot market prices known as the Real Time Market price in the Wholesale Energy Market (WEM).
“The successful energisation of the SEPP is a defining milestone for Strike and marks our transition from project execution to earnings generation,” MD and CEO, Shelley Robertson, said.
“Through this investment, we have established a strategically located 85 MW generation asset capable of supplying reliable and flexible power into a market undergoing significant structural change as State owned, coal-fired capacity retires by 2030.
“Strike has created an integrated energy asset that converts our low-cost gas reserves into long-term electricity generation revenues, adding value to our resource base while strengthening Western Australia’s energy security. The SEPP establishes a significant earnings platform for Strike, underpinned by contracted Capacity Credit revenues and upside from electricity sales.
“With energisation complete, and AEMO hold-point testing now underway, our focus turns to the commencement of commercial operations.”
Ms Robertson said the successful energisation of the South Erregulla Power Plant is substantially complete. The project is Strike’s largest growth investment undertaken to date.
A total of $187 million has been invested in the development of the project.
STX was steady at 10.5¢. Mkt cap $378.6M.
Join the discussion: See what HotCopper users are saying about Strike Energy and be part of the conversations that move the markets.
The material provided in this article is for information only and should not be treated as investment advice. Viewers are encouraged to conduct their own research and consult with a certified financial advisor before making any investment decisions. For full disclaimer information, please click here.