  • Troy Resources (TRY) has slumped on the ASX today after withdrawing its production guidance for the Karouni mine in South America
  • An October outbreak of COVID-19 infections at the Guyana mine site meant some employees had to self-isolate and others were kept off site
  • Moreover, expats have been banned from returning to Guyana and subsequently to the Karouni mine
  • To make matters worse, Troy is starting to experience spare parts shortages following a September fire at the Karouni site
  • As such, the company has scrapped its previous guidance of between 35,000 ounces and 40,000 ounces of gold at a cost of US$1500 and US$1550 per ounce (around A$2040 and A$2105 per ounce) for the 2021 financial year
  • Shares in the junior miner are down 14 per cent this afternoon and trading at 8.5 cents each

Troy Resources (TRY) has slumped on the ASX today after withdrawing its production guidance for the Karouni mine site.

The junior miner had initially forecast production of between 35,000 ounces and 40,000 ounces of gold at a cost of US$1500 and US$1550 per ounce (around A$2040 and A$2105 per ounce) for the 2021 financial year.

However, Troy said several issues have been plaguing production at the flagship South American mine, and as such, the company felt it pertinent to scrap this guidance today.

COVID blows

Not least of the issues has been a cluster of COVID-19 infections at the mine site in October. Troy said 23 positive cases were found at the site.

While the infections were dealt with effectively and impacts from the virus were minimised, the company said several employees were forced to self-isolate, dealing a blow to production.

On top of this, expats were banned from returning to Guyana, where the mine site is located, meaning some Troy employees couldn’t make it to site.

The company said Guyana is continually experiencing high levels of COVID-19 infections, which could make it tough to keep operating the Karouni mine for some time.

The September fire

On top of this, Troy is experiencing some production delays after a fire at the Karouni site in September.

The fire was contained to a storage area at the mine site and nobody was injured in the blaze. At the time, Troy said the fire had no immediate impact on production numbers but may cause some issues in the future when the company needs spare parts.

And, sure enough, Troy told investors today it has started to experience shortages of critical reagents and mill spare parts. The Karouni mill is still operational but only on a reduced basis because of the shortages.

In a small silver lining, Troy said the Hicks deposit in the Karouni area has generally reconciled very well.

Still, the production woes have been enough to drag Troy shares down 14 per cent today. At 12:58 pm AEDT, shares in TRY are trading at 8.6 cents each.

TRY by the numbers
More From The Market Online

Provident Aurum’s off-market bid sends Sihayo shares soaring

Small-cap mineral and gold explorer, Sihayo Gold (ASX:SIH) shares have soared, on news that the company…

It’s hard to imagine a world without a mining company called Anglo American

Growing up in South Africa it seemed inconceivable that Anglo American, a mining colossus at its zenith…
The Market Online Video

Geology is King: Sun Silver says Maverick Springs will outshine high-grade Australian mines

Sun Silver Ltd (ASX:SS1) is seeking gold, silver and pathfinder elements at their Maverick Springs project…

Viridis’ Brazilian holdings good for both light and heavy REEs, results beyond 27K ppm

Viridis Mining and Minerals (ASX: VMM) has remained steady on the market today on grades topping 27,000 parts per million from its rare