- Robust project economics with pre-tax payback of 18 months
- Ore reserve supports long-life, low-cost operation
- Development-ready with early works underway
- Strategic new Australian supply
Tungsten Mining (ASX: TGN) has unveiled a robust definitive feasibility study (DFS) for its Watershed tungsten project in Far North Queensland, confirming compelling project economics and a clear pathway towards a final investment decision (FID).
Chairman, Gary Lyons, said the completion of the Watershed DFS is a landmark achievement for Tungsten Mining and the culmination of an enormous effort by the company’s team and advisers.
“It marks a major step towards establishing Watershed as a significant new Australian tungsten operation,” he said.
“The DFS confirms exceptional project economics, with a pre-tax NPV of A$1.57 billion and IRR of 70% and provides a strong foundation for progressing to FID and first production.
“Importantly, Watershed has already moved beyond the study phase. With principal approvals secured, early works underway and critical long-lead procurement progressing, the Project has been substantially de-risked and is well positioned to move into full-scale construction following FID.
“Our immediate focus is on finalising binding offtake and non-equity financing arrangements in parallel to enable FID and maintain momentum towards first tungsten production in mid-2027.
“At a time of growing global demand for secure critical mineral supply, Watershed is positioned to become an important new source of Australian tungsten. I would like to acknowledge the outstanding efforts of everyone involved in reaching this milestone. Our focus now is firmly on delivering a successful operating mine and creating long- term value for shareholders.”
Global tungsten demand remains strong and is forecast to continue growing from 154 kt WO3 in 2025 to 215 kt WO3 in 2035, a compound annual growth rate of 3.4%, against current supply of 153 kt WO3.
Fastmarkets has provided an APT commodity price and payability forecast supporting projected
revenue for the Watershed Project, alongside
expected payabilities on contained metal in concentrate. The APT price forecast is displayed below through to 2035. Beyond 2035, a flat pricing and payability structure is adopted at the final forecasted price of US$1515 / mtu and 82% respectively for APT.
The company’s offtake strategy is to secure long- term agreements with a diversified mix of refiners, trading houses and metals traders across several regions.
TGN was up 2.70% to 19.0¢. Mkt cap $287.2M.
Join the discussion: See what HotCopper users are saying about Tungsten Mining and be part of the conversations that move the markets.
The material provided in this article is for information only and should not be treated as investment advice. Viewers are encouraged to conduct their own research and consult with a certified financial advisor before making any investment decisions. For full disclaimer information, please click here.