  • Vintage Energy (VEN) and its joint venture partners complete the construction of the Vali-1 leasepad facilities in preparation for first gas flows from the field
  • Mechanical handover of the facilities at Vali-1 took place on Saturday, with control handed over to a contractor to commission, operate and maintain the infrastructure
  • Commissioning is now underway, starting with the purging of the system with nitrogen to expel air and various checks prior to the introduction of gas
  • This will be followed by the commissioning of the metering facility, Beckler tie-in and export lines, with first gas from the field projected to occur within 12 days
  • Vintage Energy is up 2.25 per cent to 9.1 cents and JV partner Metgasco is down 4.55 per cent to 2.1 cents at 2:21 pm AEDT

Vintage Energy (VEN) and its joint venture (JV) partners have completed the construction of the Vali-1 leasepad facilities ahead of first gas flows from the field.

Vintage owns 50 per cent of and operates the AATP 2021 joint venture, with the remaining interest split evenly between Metgaso (MEL) and Bridgeport.

The Vali gas field, discovered by the joint venture in 2020, is in the process of being connected to the South Australian Cooper Basin gas gathering infrastructure in a bid to bring a new source of gas supply to eastern Australia.

Vali has been certified to have proved and probable gas reserves of 101 petajoules, with the JV contracted to supply between an estimated nine-to-16 petajoules of gas to AGL until 2026.

The mechanical handover of the facilities at Vali-1 took place on Saturday, with control handed over to a contractor, Upstream Production Solutions, to commission, operate and maintain the infrastructure.

Commissioning has now begun at Vali-1, starting with the purging of the system with nitrogen to expel air and various checks prior to the introduction of gas.

This will be followed by the commissioning of the metering facility, Beckler tie-in and export lines. Subject to the progress of commissioning, Vintage Energy projects first gas from the field is likely to occur within 12 days.

VEN Managing Director Neil Gibbins said the project transition from construction to commissioning marked a “long-anticipated milestone” for the company.

“Vali is now one step away from first gas, and with that the commencement of revenue generation,” Mr Gibbins told investors.

“Our focus is firmly on executing commissioning safely and efficiently so Vali gas can start flowing to eastern Australia as soon as possible.”

Construction and installation work is ongoing at the Vali-2 and Vali-3 sites, with the mechanical handover and commissioning at the sites scheduled to occur by early March.

Vintage Energy was up 2.25 per cent to 9.1 cents and JV partner Metgasco was down 4.55 per cent to 2.1 cents at 2:21 pm AEDT

VEN by the numbers
More From The Market Online
Santa stumbles no christmas this year concept Ai gen

Week 50 Wrap: Chemist Warehouse targets Feb 2025 ASX launch; no Santa Rally for Oz

The biggest news of this week as I see it is, unfortunately, depressing – the ASX200…
The Market Online Video

ASX Market Close: Oz missing out on a Santa Rally so far | 13 Dec, 2024

Welcome to HotCopper’s Market Close, and here’s to hoping you’re having a good end of the…
Bitcoin token concept

AMP becomes first super fund in Oz to invest in crypto – is it just a PR stunt?

AMP (ASX:AMP) has become the first superfund player in Australia to make a strategic investment in…
Rows of data centre processors.

Even ‘biggest IPO of the year’ fell prey to ASX investors’ seemingly unshakeable debutant indifference

Even DigiCo (ASX:DGT) and its $2.74B float – dubbed the "biggest IPO of the year" –…