Vulcan Energy (ASX:VUL) - Chair, Gavin Rezos
Chair, Gavin Rezos
Source: Business News
The Market Online - At The Bell

Join our daily newsletter At The Bell to receive exclusive market insights

  • Vulcan Energy Resources’ (VUL) pilot plant team has achieved target specification for a direct lithium extraction (DLE) feed into its pilot plant
  • The pilot plant team has achieved target recovery of greater than 90 per cent for lithium chloride from Upper Rhine Valley brine
  • The company’s next steps include the ramp up of the DLE pilot plant to 24/7 operation and production of lithium chloride solution to be converted to lithium hydroxide
  • Further work on post-treatment of brine is also scheduled before production of samples for potential customers will be sent out
  • Vulcan Energy last traded at $7.15 on May 26

Vulcan Energy Resources’ (VUL) pilot plant team has achieved target specification for a direct lithium extraction (DLE) feed into its pilot plant.

The pilot plant team achieved target recovery of greater than 90 per cent for lithium chloride from Upper Rhine Valley brine.

Vulcan is aiming to become the world’s first lithium producer with net zero greenhouse gas emissions. Its Zero Carbon Lithium Project is set to produce a battery-quality lithium hydroxide chemical product from its combined geothermal energy and lithium resource.

The Vulcan laboratory team has successfully demonstrated post-treated DLE brine to be materially the same composition as production brine, excluding extracted lithium and silica. Confirmed via the company’s first step of test work, this is in line with Vulcan’s strict environmental focus.

“We will aim to continue this momentum and to continue to rapidly de-risk and scale-up our lithium extraction process in the months to come, as we execute on our strategy to deliver our Zero Carbon Lithium Project into production for the European battery electric vehicle market,” said Vulcan Managing Director Dr. Francis Wedin.

“The team at Vulcan is highly motivated to ensure that the global transition to renewables, energy storage and electric mobility is conducted in a sustainable, net zero manner, and we are channelling this motivation into systematically executing on our Zero Carbon Lithium Project.”

The next steps will include the ramp up of the DLE pilot plant to 24/7 operation and production of lithium chloride solution to be converted to lithium hydroxide.

Further work on post-treatment of brine is also scheduled before production of samples for potential customers will be sent out.

Vulcan Energy last traded at $7.15 on May 26.

       

   

vul by the numbers
More From The Market Online

Marimaca Copper Corp hits wide copper intersection at            Pampa Medina in Chile

Marimaca Copper continues to identify wide zones of copper and silver in further assay results from…

Western Ridge Resources says exploration ramping up at new Murchison project

Western Ridge Resources has welcomed the start-up of an exploration program at its new Murchison project…
Graphic representing wrld markets.

Duratec secures over $200M in contract awards with big energy and defence wins

Duratec has secured three new contracts across its core Energy and Defence sectors, with a combined…

Forrestania Resources advances Edna May production readiness as transformation ramps up

Forrestania Resources continues to ramp-up its transitioning to gold producer status through the restart of its…