Concrete Installation Works for Fine Ore Bin Slewing Conveyer. Source: Group 6 Metals
The Market Online - At The Bell

Join our daily newsletter At The Bell to receive exclusive market insights

  • Group 6 Metals (G6M) confirms it is on target to produce its first concentrate from its wholly-owned Dolphin Tungsten Mine on King Island, Tasmania, in Q1 2023
  • The company has ramped up construction activities in line with its schedule despite a challenging environment which has impacted materials and labour availability
  • Most of the major mechanical equipment has started to arrive with the majority of the anticipated deliveries expected to arrive on-site by the end of July
  • The company expects the medium to longer term demand of ammonium paratungstate will remain strong with the easing of COVID-19 restrictions and the downstream process industry recovering
  • Shares in Group 6 are up 22.9 per cent, trading at 21.5 cents at market close

Group 6 Metals (G6M) have confirmed that it is on target to produce its first concentrate from its wholly-owned Dolphin Tungsten Mine on King Island, Tasmania, in Q1 2023.

The company had ramped up construction activities in line with its schedule despite a challenging construction environment, most recently completing the earthworks and commencing civil works required to support the process plant at the mine.

The crusher circuit is expected to be completed by the end of June which will be handed over to Gekko Systems for mechanical installation works.

Most of the major mechanical equipment has started to arrive with the majority of the anticipated deliveries expected to arrive on-site by the end of July.

CEO Keith McKnight said the company has ensured equipment will be delivered on time and within budget, mitigating significant cost escalation and delays.

“G6M staff and contractors have worked very hard to achieve the progress to date and we would like to thank them for their efforts,” he said.

“The next six months will be a very busy time for the company and our team on the ground at Dolphin.”

The overhead power line connecting the mine site to the King Island grid has been installed and trenching for the electrical conduits required to deliver power has commenced with power for construction activities expected to be made available in July.

Installation of the process plant access roads has commenced which is required for mechanical installation works due to start in July.

The company expects the medium to longer term demand of ammonium paratungstate (APT) will remain strong with the easing of COVID-19 restrictions and the downstream process industry recovering.

Shares in Group 6 were up 22.9 per cent, trading at 21.5 cents at market close.

g6m by the numbers
More From The Market Online

Alligator Energy: Perfectly positioned for next wave of Aussie uranium production

Global powers everywhere are grappling with decarbonisation and energy security, especially as nuclear power has transitioned from a side discussion to a central
The Market Online Video

ASX Today: Gold hasn’t done anything in 5 days, suggesting markets don’t see catalyst either

Greetings and welcome to HotCopper’s The ASX Today for Wednesday of Week 12, I’m Jon Davidson, and it looks like we could be in for another
Nasal spray

Two days after Tetratherix moves to GLP-1 nasal drugs, HSBC analysts say thematic overhyped

After announcing it'd be moving into the GLP-1 weight loss drugs space, Tetratherix has dropped as…

Critical Resources makes solid-state battery breakthrough

Critical Resources has made a key breakthrough in its development of a next-generation energy storage solution.