Hazer Group (ASX:HZR) - Commercial Manager, Luc Kox
Commercial Manager, Luc Kox
Source: Hazer Group/Facebook
The Market Online - At The Bell

Join our daily newsletter At The Bell to receive exclusive market insights

  • Hazer Group (HZR) pushes back the completion date for its WA commercial demonstration plant (CDP) amid overseas mill and shipping disruptions
  • The company says COVID-19 continues to impact China’s mill operations, while Hurricane Ida is causing shipping delays between Australia and China
  • In light of this, Hazer says it now expects to commission the project during the first quarter of 2022 instead of during December this year
  • Nevertheless, today’s CDP commissioning delay does not come with any further budget increases
  • Shares in Hazer Group are down 1.89 per cent today, trading at $1.04 each at 10:25 am AEST

Hazer Group (HZR) has pushed back the completion date for its Western Australian commercial demonstration plant (CDP) amid overseas mill and shipping disruptions.

The hydrogen company said this morning the COVID-19 pandemic is continuing to throw a spanner in the works for the CDP’s development as it impacts China’s mill operations.

Meanwhile, Hazer said Hurricane Ida — though it is in the United States — was also causing some shipping delays between China and Australia.

The company said the fabrication of the main reactor shell for the CDP had been delayed thanks to changes in the production schedule for the selected mill.

In light of all this, Hazer said it now planned to commission the project during the first quarter of 2022 as opposed to the previous target date of December 2021.

Still, Hazer CEO Geoff Ward said the company is pleased with the progress of the facility, especially regarding main civil works and mechanical construction.

“The Hazer reactor and furnace is a complex, first-of-kind equipment package which is being made more challenging by the current operating environment with significant disruptions to supplier operations and freight schedules due to the global COVID-19 pandemic, which has impacted the delivery time of high-temperature materials for the reactor and heat exchangers,” Mr Ward said.

“We will continue to monitor these issues and do all we can to mitigate the impacts on the project.”

Importantly, today’s CDP commissioning delay does not come with any further budget increases; Hazer said it maintained its revised guidance from June this year, expecting the facility to cost between $21 million and $22 million to build.

Hazer is developing the CDP at the Woodman Point Water Recovery Facility in WA.

Once developed, the plant will be used to showcase Hazer’s namesake hydrogen production process that is supposed to produce economically competitive hydrogen but with 50 per cent lower carbon emissions than conventional methods.

Shares in Hazer Group have slipped 1.89 per cent in early trade following today’s delay, trading at $1.04 each at 10:25 am AEST. The company has a $151 million market cap.

HZR by the numbers
More From The Market Online

EV Resources on ‘accelerated pathway’ to Los Lirios restart after strong antimony recovery tests

EV Resources is inching closer to a Los Lirios restart after strong metallurgical results set up…
Diamond drilling at Bankan.

‘Inferior’: Perseus backs down on Predictive merger – but not without swipe at Robex

Perseus Mining has thumbed its nose at Robex as it heads out the door, stepping away…
A dirt road running through the Antimony Canyon project in Utah.

American Tungsten and Antimony leaves ‘Trigg’ name behind to start next era (and set fresh focus)

American Tungsten and Antimony has entered a new era, leaving the name "Trigg Minerals" behind to…
Drill rig concept

EV Resources kicking off maiden drilling for antimony at Los Lirios, Mexico

EV Resources is geared up for a maiden drilling run right out the gate into 2026…