  • JV partners Strike Energy (STX) and Talon Energy (TPD) unveil “strong” interim results from a testing program at their Walyering onshore gas project in WA
  • The results come from individual testing of the B, C and D sands at the Walyering-5 well, with the reservoirs showing similarities to the A sand at Walyering
  • Strike says the latest results show the reservoirs have negligible impurities, and the liquids produced are of a light oil quality with minimal associated water production
  • The Strike-Talon joint venture is busy flowing the B sand and, once this is completed, will then move on to perforate and test the A sand individually
  • STX shares down 0.76 per cent to 32.8 cents and TPD shares up 5.56 per cent to one cent

Strike Energy (STX) has unveiled “strong” interim results from a testing program at its joint ventured Walyering onshore gas project near Cataby in Western Australia.

The junior energy explorer said it had completed individual testing of the B, C and D sands at the project’s Walyering-5 well.

Operator Strike holds a 55 per cent interest in Walyering in a joint venture (JV) with Talon Energy (TPD).

Strike said the B sand flowed at a maximum recorded rate of 33 million standard cubic feet per day (mmscfd) — a typical unit of measurement for natural gas flows — at 2,427 psi pressure. The B sand is currently on test.

The C sand flowed at a max rate of 32 mmscfd. The company said C sand stabilised rates were maintained for longer than 24 hours at 27 mmscfd, with flowing wellhead pressures of 2,083 psi.

The D sand flowed at a max rate of 13 mmscfd and stabilised rates were maintained for longer than 24 hours at 10 mmscfd at 813 psi.

Each of these tests was conducted through a 48/64-inch choke.

Strike said the gas streams produced in the D and C sands were similar to samples from the A sand at Walyering.

According to the company, the results show the reservoirs have negligible impurities, while the liquids produced are of a light oil quality with minimal associated water production.

The Strike-Talon JV is busy flowing the B sand and, once this is completed, will then move on to perforate and test the A sand individually.

The flowing work would be followed by a series of pipework upgrades across the testing package to ensure the equipment can handle the higher-than-expected rates of the final comingled test from all four reservoirs.

Strike and Talon have also spudded Walyering-6 and are drilling ahead in the top section of the well at about 969 metres measured depth (MD). The JV plans to drill Walyering-6 down to just over 3,500m MD.

STX shares were down 0.76 per cent to 32.8 cents and TPD shares were up 5.56 per cent to one cent at 1:32 pm AEST.

STX by the numbers
More From The Market Online

Market Close: Green light launches ASX lift off as US inflation ebbs

The ASX200 closed nearly 1.6% up. Every sector – aside from energy – ended in the green.
The Market Online Video

Market Update: ASX accelerates ahead of future forecasts

The ASX200 delivered a sweet surprise this morning, surging 1.7 per cent to deliver growth far in excess of future’s predictions.

The home PC changed retail stores forever. Shekel Brainweigh can do it again

Retail store automation demands tech to prevent shoplifting and give business owners peace of mind. Shekel…

Pivotal Metals unveils copper continuity at Quebec play Horden Lake

Drilling work at the Horden Lake project in Quebec has revealed continuously thick zones of copper…