Manusela limestone- Neif Gorge, Seram Island. Source: Lion Energy
The Market Online - At The Bell

Join our daily newsletter At The Bell to receive exclusive market insights

  • Lion Energy (LIO) will soon undertake a test of the Lofin-2 well, located onshore of Indonesia, following approval from joint venture partners
  • The test work is aimed at improving the understanding of the reservoir characteristics and according to LIO, is critical to planning commercialisation of the wider Lofin gas field
  • The Seram (NonBula) PSC joint venture parties plan to conduct the test in mid 2022 following receipt of the required long lead items
  • A staged development plan is anticipated with potential for initial gas sales during extended well testing, the results of which will guide the full development plan
  • Company shares have been trading grey at 6.1 cents

Lion Energy (LIO) will soon undertake a test of the Lofin-2 well, located onshore of Indonesia, following approval from its joint venture partners.

Lion holds the largest land position on Seram Island, East Indonesia — which hosts the Lofin gas discovery.

LIO has a 2.5 per cent working interest in the Seram (Non Bula) Production Sharing Contract (PSC) area and is the operator of the East Seram PSC.

In 2015, the well reportedly delineated a continuous gas column of 1300 metres, marking one of Indonesia’s largest recent onshore gas discoveries.

According to Lion, the upcoming test work will enable critical fluid and reservoir information to be obtained and will be key to planning commercialisation of the Lofin gas field.

In particular, the well test is hoped to improve the understanding of the reservoir characteristics, re-affirm the contingent resource estimate and assess the gas deliverability of the well for early commercialisation.

Moreover, the objective of the testing is to enable preparation of a ‘Put-On-Production’ application with the Indonesian regulatory body, SKK Migas, under which the joint venture would produce gas from the existing well.

The Seram (NonBula) PSC joint venturers plan to conduct the test in mid 2022 following receipt of the required long lead items.

It is set to cost US$12.3 million (A$17.2 million), with Lion to pay US$300,000 (A$421,517).

Of the total amount, the JV has already paid around US$1 million (A$1.4 million)

A staged development plan is anticipated with the potential for initial gas sales during extended well testing, the results of which LIO said will guide the full development plan.

Lion’s Chairman Tom Soulsby said the company was looking forward to the testing, which he said marks a key step in the commercialisation of the Lofin gas resource.

“The testing program forms part of an exciting 2022 for Lion on Seram island as we will also be conducting a 200 kilometre onshore seismic survey in our East Seram PSC which will target an impressive inventory of prospects and leads some of which are analogous to the Lofin field,” he said.

At market close on Tuesday, company shares were trading grey at 6.1 cents.

LIO by the numbers
More From The Market Online

Lithium Universe ends the quarter charged up for Quebec Refinery roll-out

Lithium Universe has closed off the March quarter with a new Chief Financial Officer and strategically located land…

Alligator snaps at extended mineralisation of Blackbush uranium deposit in SA

Extension drilling in the first four months of this year at the Samphire Uranium Project in South Australia has enabled Alligator Energy Ltd
The Market Online Video

Market Update: Red flags dot ASX landscape as living costs squeeze

The ASX200 is down 1.1 per cent – on par with futures’ predictions – with every sector flashing red mid-session.

Mine study work sees 70% boost in gold resource for Nexus in WA’s Goldfields

Nexus Minerals has bumped up the Crusader-Templar combined mineral resource estimate by more than 70% at…