Calima Energy (ASX:CE1)
Installation of 6” Pipeline at Brooks. Source: Calima Energy.
The Market Online - At The Bell

Join our daily newsletter At The Bell to receive exclusive market insights

  • Calima Energy’s (CE1) pipeline infrastructure is progressing ahead of schedule and on budget at its Brooks project in Alberta, Canada.
  • During February, well maintenance activities and pipeline construction resulted in average production above 4,200 barrels of oil equivalent per day (boe/d).
  • The pipeline connects Calima’s oil battery in the north to the recently drilled Gemini wells in the south to provide egress for planned production growth.  
  • The Gemini #6 well is on production while Gemini #5, Gemini #7 and Pisces #3 will be brought on production within the next two weeks.
  • Shares in CE1 were trading 2.17 per cent lower at 22.5 cents.

Calima Energy’s (CE1) pipeline infrastructure is progressing ahead of schedule and on budget at its Brooks project in Alberta, Canada.

During February well maintenance activities and pipeline construction resulted in average production above 4,200 barrels of oil equivalent per day (boe/d).

The pipeline connects Calima’s oil battery in the north to the recently drilled Gemini #5, #6 and #7 and Pisces #3 wells in the south to provide egress for planned production growth.  

The Gemini #5 and #6 wells are now tied into the pipeline.

Gemini #7 will be tied-in within a week and Pisces #3 will be tied in by mid-March.

Gemini #6 is on production while Gemini #5, Gemini #7 and Pisces #3 will be brought on production within the next two weeks.

Pisces #3 has been fracture stimulated and will be flowing back post the next seven-day shut-in period.

The final section of the pipeline is expected to be connected and flowing into the battery by the end of March.

Chief Executive Officer and President Jordan Kevol said the company is very pleased with progress in the field at Brooks.

“Before the winter frost melts, the team is focused on the Bantry Field at Brooks to equip and tie-in the four wells currently behind pipe (Gemini and Pisces),” said Mr Kevol.

“We are ahead of our goal of having Gemini #5, #6, #7, and Pisces #3 on production by the end of March which will positively contribute to current cash flow and our H1 2022 average production of 4,000-5,000 boe/d.”

Shares in CE1 were trading 2.17 per cent lower at 22.5 cents.

ce1 by the numbers
More From The Market Online

Amplitude Energy purchases Artisan gas field from Beach Energy

Amplitude Energy plans to fast-track development of the Artisan gas field and the ECSP in the…

‘We expect the grade to improve’: Meeka intersects first development ore at Judy North

Meeka Metals is ramping up activities in WA with the continued expansion of development at the…
The ASX Today feature image with a blue Australia silhouette (STOCK) beside The Market Link column branding.

The ASX Today: Aussies eventually warm up to peace news; Qantas jumps, Wall Street futes green

Greetings and welcome to HotCopper’s the ASX Today for Monday of Week 22, I’m Jonathon Davidson, and while the ASX eventually reacted positively to the Donald

Desert Metals extends Tiogo gold anomaly with soil sampling at Tengrela South

Desert Metals has identified a significant new target at its Tengrela South gold project in northern…