  • Buru Energy (BRU) progresses operations in Western Australia’s Canning Basin
  • Following spudding of the Rafael-1 well last month, BRU has set a surface conductor and drilled the well ahead to a section depth of 1652 metres
  • The company has also installed casing and conducted pressure testing at Rafael
  • Meanwhile BRU is gearing up for a final test program at the Currajong-1 well this month, with the completion equipment on its way to site
  • Shares are sitting steady at 14.3 cents at 2:02 pm AEST

Buru Energy (BRU) has updated shareholders on its operations in Western Australia’s Canning Basin.

Rafael-1 drilling operations

Last month the company spudded the Rafael-1 well, which is is situated on exploration permit EP428, some 50 kilometres east of the Ungani Oilfield and roughly 150 kilometres east of Broome.

Since then, the 508-millimetre surface conductor has reportedly been set at 130 metres’ measured depth and the well drilled ahead to a section depth of 1652 metres in a 445-millimetre hole.

BRU said the 340-millimetre casing had also been installed to a measured depth of 1649 metres and successfully pressure tested.

The current operation is drilling ahead in a 311-millimetre hole to the 244-millimetre casing setting depth above the interpreted reservoir section, which will in turn be drilled in a 216-millimetre hole after casing has been set.

Currajong-1 well testing program

Meanwhile, the company is gearing up for a final test program at the Currajong-1 well, with additional equipment being mobilised to site from the manufacturers.

Installation of this equipment is planned to commence in mid-September, once all components are on site, followed by the flow test program later in the month.

Buru is planning to individually test four zones in the dolomite section ahead of a combined flow test once the individual activities have been completed.

All up, testing is expected to take up to two weeks.

Shares were sitting steady at 14.3 cents at 2:02 pm AEST.

BRU by the numbers
More From The Market Online

Firebrick Pharma sees substantial holder up stake to 12% in placement

Betadine-like nasal spray provider Firebrick – whose flagship product has recently gone live for sale in…

BPH Energy reveals high-profile firms included in latest $1M placement

BPH Energy is raising $1M to help assist with the development of its two main activities…

D3E joins ASX as it hunts natural gas and helium in South Africa

D3E Energy will begin trading on the Australian Stock Exchange at 11 am today, having listed…

Kinetiko says it’s the first to produce power from onshore gas in S. Africa

Kinetiko Energy (ASX:KKO) has made its own footnote in history books on Tuesday, the first to…