  • Hillgrove Resources (HGO) makes a final investment decision to proceed with the stage one development of its Kanmantoo underground copper mine in South Australia
  • The project is being fully funded by a recent $38 million placement and share purchase plan
  • Stage one aims deliver 43.5 thousand tonnes of copper in concentrate over the initial four-year schedule
  • Hillgrove remains on track for first copper concentrate production in the first quarter of 2024
  • Shares in HGO is up 3.64 per cent, trading at 5.7 cents at 12:30 pm AEST

Hillgrove Resources (HGO) has made a final investment decision to proceed with the stage one development of its Kanmantoo underground copper mine in South Australia.

The company’s underground development of Kanmantoo started in May in anticipation of a positive investment decision.

The project is being fully funded by a recent $38 million placement and share purchase plan, providing the company with adequate funding to reach sustainable copper production in stage one and also continue exploring to increase the mine’s life and production.

HGO Managing Director Lachlan Wallace said the final investment decision marked an “exciting” milestone for the company.

“Drilling over the past three years has successfully increased the mineral resource estimate by 600 per cent, to almost seven million tonnes, and with an exploration target of a further 10 to 20 million at 0.9 to 1.3 per cent copper and 0.1 to 0.3 grams per tonne (g/t) gold in close proximity to the processing plant, there is a great opportunity to expand the mine life further,” he said.

Hillgrove announced that stage one would look to deliver 43.5 metric tons of copper in concentrate over the initial four-year schedule.

The company also reported it has entered underground mining contracts and appointed key employees to guide the underground development, with the company on track for first copper production in the first quarter of 2024.

“It’s fantastic to see the Kanmantoo copper mine reaching financial investment decision and on track to produce first copper early next year,” Minister for Infrastructure, Transport, Energy & Mining Hon. Tom Koutsantonis said.

“Copper is arguably the most important critical mineral as the world looks to decarbonise.

“Mines such as this stand to help address the copper deficit while stimulating the state and local economy.”

Hillgrove said with all infrastructure, including a 3.6 million tonne per annum processing plant and operational tailings storage facility already in place, the cost and risk to first copper production remained relatively low.

Shares in HGO was up 3.64 per cent, trading at 5.7 cents at 12:30 pm AEST.

hgo by the numbers
More From The Market Online

KGL Resources jumps 25% on US$300M funding deal

KGL Resources has entered into a US$300 million PMPA to help fund construction and development of…
London

With osteo Phase 3 trial at 50% recruitment, Paradigm Bio inks partnership with University of London

Paradigm Biopharma (ASX:PAR) has this week hit two big items out the park: first of all, hitting 50% recruitment

Terra hits multiple intersections at Southwest SW6 prospect; assays now due in next ~12 weeks

Terra Metals has hit multiple intersections of massive sulphides in drilling at the Southwest SW6 prospect…
Easter bunny in a business suit analyzing stock charts, symbolizing market strategy

ASX closed for Easter long weekend. Enjoy your chocolates and the holiday break!

Yes, yes, I know you’re itching to do some serious Australian market trading today, but everyone — especially our much-loved HotCopper forum users