St Barbara (ASX:SBM) - Managing Director & CEO, Craig Jetson
Managing Director & CEO, Craig Jetson
Source: The Mining Journal
The Market Online - At The Bell

Join our daily newsletter At The Bell to receive exclusive market insights

  • St Barbara (SBM) has announced its Simberi Sulphide Project will move to the feasibility study phase after an encouraging pre‐feasibility study
  • In March, the company completed an updated version of the 2016 pre-feasibility study
  • The study confirmed the potential for an extended mine life to the 2035 financial year
  • The study also outlined a 38 per cent increase in sulphide ore reserves, and an 80 per cent increase in total gold produced
  • The ASX 200 lister is focused on low capex solutions that utilise existing facilities
  • St Barbara expects the next-stage feasibility study will be completed in December this year
  • St Barbara’s shares are down a slight 0.40 per cent and are trading for $2.51 each

St Barbara (SBM) has announced its Simberi Sulphide Project will move to the feasibility study phase after an encouraging updated pre‐feasibility study.

In March this year, the company completed an update of the 2016 pre-feasibility study (PFS). The PFS was then validated by an independent review which has confirmed the potential to extend the project mine life to the 2035 financial year.

Other key changes from the 2016 PFS to the 2020 PFS include a 38 per cent increase in sulphide ore reserves from 1.3 million ounces to 1.8 million ounces, a 40 per cent increase in capital expenditure from US$100 million to between US$130 and $150 million.

The PFS also outlined an 80 per cent increase in total gold produced from 1 million ounces over eight years to 1.8 million ounces over 13 years.

The ASX 200-lister strategised the updated PFS to focus on low capex solutions that utilise existing infrastructure on the Simberi Island where the project is situated in Papua New Guinea.

Current infrastructure includes the airport, power station, village and wharf. The existing semi‐autogenous grinding (SAG) mill will be utilised in a new plant flowsheet to maintain the ability to process oxide and sulphide ores separately.

The PFS also indicates the preferred option is the production and sale of a concentrate. This avoids the need to establish downstream processing facilities on the island.

St Barbara expects to complete the next-stage feasibility study and Environmental and Social Impact Assessment in December this year.

The study anticipates a two-year construction phase, commencing in the 2021 March quarter. As previously reported, the Simberi mining lease (ML136) is valid until December 2028.

St Barbara’s shares are down a slight 0.40 per cent and are trading for $2.51 each at 1:15 pm AEST.

sbm by the numbers
More From The Market Online

‘Case of the century’ starts today with ACCC taking Coles to Federal Cour over ‘Down, Down’ deals

The Australian Competition and Consumer Commission and Coles (ASX:COL) are all set to face off in Federal Court today, after the ACCC
Calendar

Here’s the 10 company earnings that matter to come in February for ASX investors

We’re halfway through earnings Down Under, and we’ve had a reminder through Week 7 that the event really does drive markets, what with

NZ gov’t bites bullet and confirms LNG import plans to help ‘exposed’ elec sector

Australia and Papua New Guinea are likely to be at the forefront of discussions to supply…
Close up of CSL sign on the office building in Melbourne, Victoria, Australia.

CSL profit drop only deepens what has already been grim reporting week

CSL Ltd has backed up its chaotic Tuesday – where the board dumped Paul McKenzie –…